Evaluation of Time Performance in Construction Project Implementation: A Case Study of Building X and Building Y
Abstract
This study aims to evaluate the implementation of construction project time management in the Building Development Project at RSUD X. The research focuses on analyzing the conformity between planned schedules and actual project execution, identifying time deviations, determining critical path activities, and examining factors causing delays during project implementation. The study employed a descriptive quantitative approach with a case study method. Data were collected through observation, documentation, interviews, project schedules, S-curve data, and weekly progress reports. The analysis was conducted using S-Curve comparison and Critical Path techniques to evaluate project performance in terms of time control. The findings indicate that several project activities experienced delays caused by technical, managerial, and external factors, including material delivery constraints, coordination issues, and field conditions. Critical path analysis identified several key activities that significantly influenced the overall project duration. The study concludes that effective time management, continuous monitoring, and proper scheduling control are essential to minimize delays and improve construction project performance.
References
Ahman, R. I., Habir, & Arifin, B. M. E. (2025). Time performance and project progress analysis of the KM 13 Samboja Government Building Project based on the realized schedule. World Journal of Civil Engineering, 6(1).
Astari, N. M., Subagyo, A. M., & Kusnadi. (2021). Project management planning using CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) methods. Journal of Construction, 13(1), 164–180. https://doi.org/10.24853/jk.13.1.164-180
Astari, N. M., Subagyo, A. M., & Kusnadi. (2021). Project management planning using CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) methods. Konstruksia, 13(1), 164–180. https://doi.org/10.24853/jk.13.1.164-180
Ayatullah, M. A., Sarmingsih, A., & Syafrudin. (2025). Time management analysis in the Garuda East Parang Road Construction Project in Kendal Industrial Estate. http://ejournal.undip.ac.id/index.php/jpii
Diandra, N. (2025). Analyzing construction schedule deviation using S-Curve: A residential project case. Journal of Technology and Design, 1(1), 58–68. https://doi.org/10.51170/jtd.v1i1.115
Diandra, N. (2025). Analyzing construction schedule deviation using S-Curve: A residential project case. Jurnal Teknologi dan Desain, 1(1), 58–68. https://doi.org/10.51170/jtd.v1i01.115
Dicky, A., Mulyati, E., & Artikel, R. (2025). Abstract article info. 4(3), 210–217. https://doi.org/10.55123
Fahruri Munasir, U., A.Y. Tromol Pos, J., & Kartasura, P. (2025). Time management in the lower structure of the Surakarta Kasih Ibu Hospital construction project.
Juliarta, I. W. T., Yana, A. A. G. A., & Dewi, A. D. P. (2024). Strategies for handling delays in building projects (private) during the construction period in Badung Regency. Journal of Asian Multicultural Research for Economy and Management Study, 5(4), 19–28.
Kania, R., Febriani, R., Maharani, D., Hendra, Y., & Rakhmat, E. (2025). Perancangan sistem manajemen proyek menggunakan Critical Path Method (CPM) di PT Adhi Putra Bangun Perkasa. Jurnal Ilmiah Sains dan Teknologi, 9(2), 254–265. https://doi.org/10.47080/saintek.v9i2.4151
Khohar, A., Didik Budi Fariadi, I. S., & Person, K. (2021). Application of time management to construction project completion, case study: Construction of Stroke Service Center Building of Haji General Hospital Surabaya 2020. Engineering Seminar.
Khotimah, I. H., Sholahuddin, M., Rodhi, N. N., & Tjandra, A. (2024). Project time control analysis uses the Critical Path Method (CPM). Journal of Civil Engineering, 9(2), 60–69.
Khotimah, I. H., Sholahuddin, M., Rodhi, N. N., & Tjandra, A. (2024). Analisis pengendalian waktu proyek menggunakan metode Critical Path Method (CPM): Studi kasus proyek rehabilitasi Jalan Dander–Bubulan. De’Teksi: Jurnal Teknik Sipil, 9(2), 60–69.
Mardiaman, & Siregar, J. (2023). Analisis deviasi kemajuan pekerjaan berdasarkan persentase durasi waktu pada pekerjaan konstruksi bangunan. Menara: Jurnal Teknik Sipil, 18(1), 59–65. https://doi.org/10.21009/jmenara.v18i1.29213
Mardiaman, & Siregar, J. (2023). Analysis of work progress deviation based on the percentage of time duration on building construction work. Journal of Civil Engineering, 18(1), 59–65. https://doi.org/10.21009/jmenara.v18i1.29213
Nugraha, D. N. P., & Titisari, M. A. (2024). Penerapan Critical Path Method dalam penjadwalan proyek pemasangan tangki storage ST-1812, studi kasus pada PT. MSM. Jurnal Ilmiah Teknik Industri, 12(2), 143–150.
Papua, M., Dewita, H., & Sembiring, K. (2023). Analisis penjadwalan dengan menggunakan time schedule Kurva S pada proyek pembangunan Kantor Cabang BRI Otista Jakarta Timur. Jurnal Teknika, 15(1), 9–22. https://doi.org/10.30736/jt.v15i1.916
Papua, M., Dewita, H., & Sembiring, K. (2023). Scheduling analysis using time schedule Curve S in the construction project of BRI Otista Branch Office in East Jakarta. Technical Journal, 15(1), 9–22. https://doi.org/10.30736/jt.v15i1.916
Permatasari, T. R., Setyaning, L. B., & Aziz, U. A. (2023). Analisis penjadwalan menggunakan metode Critical Path Method (CPM) pada pembangunan Gedung Dindikbud Kabupaten Purworejo. Surya Beton: Jurnal Ilmu Teknik Sipil, 7(2), 169–175.
Permatasari, T. R., Setyaning, L. B., & Aziz, U. A. (2023). Scheduling analysis using the Critical Path Method (CPM) in the construction of the Purworejo Regency Education and Culture Building. Journal of Concrete Solar, 7(2), 169–175. https://jurnal.umpwr.ac.id/suryabeton/article/view/3765
Putra, N. L., Patriadi, A., & Sajiyo. (2025). Analysis of mitigation strategies for project delay factors in the Probolinggo Square construction. Devotion: Journal of Research and Community Service, 6(3).
Putri, D. C., Witjaksana, B., & Tjendani, H. T. (2024). Time delay analysis using Critical Path Method (CPM): Case study Kerobokan Bali Parking Building Construction Project. International Journal on Advanced Technology, Engineering, and Information System, 3(4), 502–517. https://doi.org/10.55047/ijateis.v3i4.1189
Rauzana, A., & Dharma, W. (2022). Causes of delays in construction projects in the Province of Aceh, Indonesia. PLOS ONE, 17(1), Article e0263337. https://doi.org/10.1371/journal.pone.0263337
Ridwan, A. (2025). Optimizing project time management using the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT). Jurnal Aplikasi Pelayaran dan Kepelabuhanan, 15(2), 354–361. https://doi.org/10.30649/japk.v15i2.160
Schuldt, S. J., Nicholson, M. R., Adams, Y. A., & Delorit, J. D. (2021). Weather-related construction delays in a changing climate: A systematic state-of-the-art review. Sustainability, 13(5), Article 2861. https://doi.org/10.3390/su13052861
Sulistia, D., & Agustina, I. D. (2023). Scheduling projects with an S-Curve in housing development in Bekasi City. Al Ulum Journal, 11(2), 100–106. https://doi.org/10.47662/alulum.v11i2.540
Suramli, S., Rachman, K. A., Dewi, N. F., Novianda, D. S., & Surahman, S. (2025). Critical path analysis scheduling project with Critical Path Method (CPM) using application Microsoft Project on Type 78 house construction project. Enrichment: Journal of Management, 15(2), 73–81. https://doi.org/10.35335/enrichment.v15i2.2263
Surri, D. A., & Alfianto, I. (2025). Factors causing delays in infrastructure projects in Indonesia and their management strategies: A literature study. Journal of Sustainable Construction, 5(1), 25–34. https://doi.org/10.26593/josc.v5i1.9253
Susanti, R., Fauziyah, S., & Suwarto, F. (2021). Assessing factors towards construction project delays in Indonesia. IOP Conference Series: Earth and Environmental Science, 700(1), Article 012064. https://doi.org/10.1088/1755-1315/700/1/012064
Syafira Aulia, P., Yogaswara, I. B., Widyastuti, L., Psi, S., & Psi, M. (2025). Performance analysis of BKD Karanganyar Office Construction Project Management using Earned Value Method.
Talang Rasa, B., & Handayani, K. D. (2023). Construction project performance evaluation reviewed from the cost and time aspect using the Earned Value Analysis Method case study: Construction of the Office Building of the Bengawan Solo River Area Center (BBWS). PORTAL: Journal of Civil Engineering, 15(2), 12–19.
Tariq, J., & Gardezi, S. S. S. (2023). Study the delays and conflicts for construction projects and their mutual relationship: A review. Ain Shams Engineering Journal, 14(1), Article 101815. https://doi.org/10.1016/j.asej.2022.101815
Vazquez, A., Marasinou, C., Kalogridis, G., & Ellinas, C. (2024). Activity delay patterns in project networks. Physica A: Statistical Mechanics and Its Applications, 637, Article 129570. https://doi.org/10.1016/j.physa.2024.129570
Vazquez, A., Pozzana, I., Kalogridis, G., & Ellinas, C. (2023). Activity networks determine project performance. Scientific Reports, 13, Article 509. https://doi.org/10.1038/s41598-022-27180-0
Zai, E. O., Saragi, Y. R., & Telaumbanua, W. A. (2024). Analysis of the application of time management of structural work in the construction project of the Dermina Beach & Cottage Samosir Building. Journal of Civil Engineering, 4(1), 29–41.
Copyright (c) 2026 Journal La Multiapp

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.