Analysis of Improving the Efficiency and Effectiveness of Company Resource Utilization Using CPM and PERT Approaches: A Case Study

  • Wagimin Department of Industrial Engineering, Faculty of Electrical Engineering, Balikpapan University, Indonesia
  • Anwar Fattah Department of Industrial Engineering, Faculty of Electrical Engineering, Balikpapan University, Indonesia
Keywords: Project Management, Critical Path Method, PERT, Project Scheduling, Resource Efficiency

Abstract

Effective project management is essential for technology service companies to improve resource efficiency and minimize project delays. PT XYZ has experienced an increase in project demand, but several projects have not been completed according to the planned schedule, resulting in financial losses and potential client dissatisfaction. This study aims to analyze the scheduling of the Hospital Informatics Project at PT XYZ using the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT). A descriptive quantitative case study approach was applied by identifying project activities, determining activity dependencies, allocating human resources, developing a project network, and calculating project duration and completion probability. The CPM analysis shows that the critical path of the project is C–F–H–J, with an optimal completion time of 45 months. The PERT analysis indicates that the probability of completing the project within the target duration is 24.51%. The findings also show that project delays may be influenced by work methods, environmental conditions, material availability, human resources, and extraordinary circumstances. Therefore, the integration of CPM and PERT can help PT XYZ improve project scheduling, monitor critical activities, reduce delay risks, and enhance the efficiency and effectiveness of company resources.

References

Agyei, W. (2015). Project planning and scheduling using PERT and CPM techniques with linear programming: case study. International journal of scientific & technology research, 4(8), 222-227.

Ahmad, N. R. (2025). Monetary policy, inflation and unemployment: The interactions and their economic impacts in Pakistan. Journal of Business and Management Research, 4(1), 954-970.

Ahmed, I., Munir, F., Nafees, F., Mahmood, J., Chaudhry, S. A., Javaid, M., & Batool, K. (2024, December). The Influence of Kanban Agile Methodology on Software Project Management: A Survey Method. In 2024 International Conference on Engineering and Emerging Technologies (ICEET) (pp. 1-6). IEEE. https://doi.org/10.1109/ICEET65156.2024.10913653

Ahmetoglu, Y., Iskandar, A., Taoh, S., Ying, A., Brumby, D. P., & Cox, A. L. (2025, June). " I Work Much Better by Doing Less": How Task Duration Feedback Affects Optimistic Planning Bias in Academic Work. In Proceedings of the 4th Annual Symposium on Human-Computer Interaction for Work (pp. 1-17). https://doi.org/10.1145/3729176.3729182

Alt, R., Auth, G., & Kögler, C. (2018). Transformation of Consulting for Software-Defined Businesses: Lessons from a DevOps case study in a German IT company. In Advances in consulting research: Recent findings and practical cases (pp. 385-403). Cham: Springer International Publishing. https://doi.org/10.1007/978-3-319-95999-3_19

Andiyan, A., Putra, R. M., Rembulan, G. D., & Tannady, H. (2021, June). Construction project evaluation using CPM-Crashing, CPM-PERT and CCPM for minimize project delays. In Journal of Physics: Conference Series (Vol. 1933, No. 1, p. 012096). IOP Publishing. https://doi.org/10.1088/1742-6596/1933/1/012096

Astari, N. M., Subagyo, A. M., & Kusnadi, K. (2021). Perencanaan manajemen proyek dengan metode CPM (Critical Path Method) dan PERT (Program Evaluation and Review Technique). Konstruksia, 13(1), 164–180. https://doi.org/10.24853/jk.13.1.164-180

Atin, S., & Lubis, R. (2019, November). Implementation of critical path method in project planning and scheduling. In IOP Conference Series: Materials Science and Engineering (Vol. 662, No. 2, p. 022031). IOP Publishing. 10.1088/1757- https://doi.org/ https://doi.org/899X/662/2/022031

Aulia, S., & Cipta, H. (2023). Network planning analysis using CPM and PERT methods on optimization of time and cost. Sinkron: Jurnal dan Penelitian Teknik Informatika, 8(1), 171–177. https://doi.org/10.33395/sinkron.v8i1.11961

Bachmid, S., Ramadhani, A. F., Watono, W., & Arsal, S. F. (2022). Perbandingan Critical Path Method (CPM) dengan Program Evaluation and Review Technique (PERT) terhadap penjadwalan waktu proyek. Jurnal Teknik Sipil MACCA, 7(2), 157–167. https://doi.org/10.33096/jtsm.v7i2.660

Barua, C. (2026). A Meta-Analysis of Deep Reinforcement Learning for Dynamic Project Scheduling in Engineering Systems. American Journal of Interdisciplinary Studies, 7(01), 578-616. https://doi.org/10.63125/t5h1bc22

Cinkusz, K., Chudziak, J. A., & Niewiadomska-Szynkiewicz, E. (2024). Cognitive agents powered by large language models for agile software project management. Electronics, 14(1), 87. https://doi.org/10.3390/electronics14010087

Dimyati, D. H., & Nurjaman, K. (2014). Manajemen proyek. Pustaka Setia.

Duncan, W. R. (1996). A guide to the project management body of knowledge. PMI Communication.

Fauzah, D., Setyawan, R., Laksmi, A. A., & Soebakti, S. A. (2024). Optimizing project scheduling using CPM and PERT methods: Case study Pejambon 8-storey flat, Central Jakarta. Jurnal Ilmiah Teknik Sipil, 28(2), 116–131. https://doi.org/10.24843/JITS.2024.v28.i02.p02

Feliu-Talegón, D., Rafee Nekoo, S., Tapia, R., Acosta, J. Á., & Ollero, A. (2026). Practical fractional-order terminal sliding-mode control for a class of continuous-time nonlinear systems. Transactions of the Institute of Measurement and Control, 48(1), 19-32. https://doi.org/10.1177/01423312241286352

Firdaus, R. S., & Hermawan, H. (2025). Analysis and Application of Construction Management in The Waled-Ciledug BTS Road Reconstruction Project. Jurnal Syntax Transformation, 6(2), 129-143. https://doi.org/10.46799/jst.v6i2.1065

Firmansyah, B., Ipung, H. P., & Soetomo, M. A. (2025). Evaluation of IT Governance With a Focus on Business Application Continuity Using the Cobit 2019 Framework: A Case Study in XYZ Group. Jurnal Ilmiah Multidisiplin Indonesia (JIM-ID), 4(10), 1423-1462.

Galster, M., Mitrovic, A., Malinen, S., & Holland, J. (2022, September). What soft skills does the software industry* really* want? An exploratory study of software positions in New Zealand. In Proceedings of the 16th ACM/IEEE International Symposium on Empirical Software Engineering and Measurement (pp. 272-282). https://doi.org/10.1145/3544902.3546247

Goda, D. R., Vadiyala, V. R., Yerram, S. R., & Mallipeddi, S. R. (2023). Dynamic programming approaches for resource allocation in project scheduling: maximizing efficiency under time and budget constraints. ABC Journal of Advanced Research, 12(1), 1-16.

Gupta, S., George, R. C., Philip, D., & Nair, S. (2025). Data-Driven Decision Framework for Modeling and Quantification of Uncertainty and Variability in Construction Project Scheduling. Journal of Structural Design and Construction Practice, 30(4), 04025078. https://doi.org/10.1061/JSDCCC.SCENG-1817

Hadicara, D., Rochim, A., & Pratikso, P. (2023). Penggunaan metode PERT dan CPM dalam proyek pembangunan jalan. Pondasi, 28(1).

Hanifa, P., Megawati, L., & Wahidin, W. (2024). Scheduling analysis of oil tank maintenance project system coil heater pipe factory using CPM method (Critical Path Method) and PERT (Project Evaluation and Review Technique). INVEST: Jurnal Inovasi Bisnis dan Akuntansi, 5(1), 102–107. https://doi.org/10.55583/invest.v5i1.634

Hanifudin, M., & Satrio, H. (2026). Effectiveness of Software Project Management Based on Capability Maturity Model Integration in the Implementation of Secure Software Development Life Cycle at PT XYZ. Indonesian Interdisciplinary Journal of Sharia Economics (IIJSE), 9(2), 11758-11769. https://doi.org/10.31538/iijse.v9i2.10085

Hansen, S., Fassa, F., & Wijaya, S. (2023). Factors influencing scheduling activities of construction projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 15(1), 06522004. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000594

Haque, F., & Mathur, V. S. (2025). Construction Project Planning and Scheduling. In Handbook of Construction Project Management (pp. 135-187). Singapore: Springer Nature Singapore. https://doi.org/10.1007/978-981-96-7631-6_5

Husna, R. A., Ilmiyah, N. F., & Resti, N. C. (2022). Implementasi CPM dan PERT dalam memprediksi durasi serta biaya pembangunan Musala Al-Ikhlas di Kotawaringin Barat. Journal Focus Action of Research Mathematic (Factor M), 5(1), 97–109. https://doi.org/10.30762/f_m.v5i1.633

Joshi, K., & Singh, V. K. (2023). The Future of Software Development Consulting: How AI Technologies Might Impact This Industry? An Interview with Srini Rajnikanth, Founder & CEO, Gemini Consulting and Services, St Louis, USA. Journal of Global Information Technology Management, 26(3), 254-260. https://doi.org/10.1080/1097198X.2023.2237730

Jufiter, R., Rajagukguk, W., & Tewu, M. D. (2026). SWOT Analysis and Action Plan Development in Strategic Risk Audit: A Case Study of PT XYZ. Jurnal Manajemen Motivasi, 22(1), 3380-3393. https://doi.org/10.29406/jmm.v22i1.9179

Larasati, V. W., Murtini, S., Raharjanti, R., & Marliyati, M. (2023). ITIL Framework 3: Analysis of Management Information Technology Services at XYZ Hospital in Semarang. Asian Journal of Management, Entrepreneurship and Social Science, 3(02), 350-361.

Latifah, I., & Safrida, I. (2025). Improving Students' Language Skills with Punakawan Wayang Media at RA Mansyaul Huda: A Classroom Action Research. Journal of Indonesian Primary School, 2(1), 13-24. https://doi.org/10.62945/jips.v2i1.415

Lubis, A. M., Widyarini, M., & Sunardi, O. (2023). Risk mitigation in supply chain disruption during pandemic covid-19 in EPC project, study case Pt Xyz. Jurnal Ekonomi, 12(04), 1404-1416.

Muchtiar, M., Narimawati, U., & Kurniawan, B. (2026). THE ROLE OF HOSPITAL MANAGEMENT IN PRODUCTIVITY, REVENUE, EFFICIENCY, AND EFFECTIVENESS OF JKN PATIENT SERVICES: A CASE STUDY OF A PRIVATE HOSPITAL (XYZ) IN INDONESIA, 2023–2024. Multidisciplinary Research Studies in Social Sciences, 2(1), 38-49. https://doi.org/10.71312/mrscholar.v2i1.811

Nasution, S. N. A., & Tanjung, A. A. (2026). Implementation of Network Planning in the Shophouse Construction Project in Tanjung Morawa District, Deli Serdang Regency. Journal of Business Economics and Management| E-ISSN: 3063-8968, 2(3), 2122-2129.

Papke-Shields, K. E., & Boyer-Wright, K. M. (2017). Strategic planning characteristics applied to project management. International Journal of Project Management, 35(2), 169-179. https://doi.org/10.1016/j.ijproman.2016.10.015

Pellerin, R., & Perrier, N. (2019). A review of methods, techniques and tools for project planning and control. International Journal of Production Research, 57(7), 2160-2178. https://doi.org/10.1080/00207543.2018.1524168

Perrucci, D. V., Wilson, J., Brown, R., Mireles Camey, J., Doktycz, C., Perry, M., & Buitrago, G. C. (2025). Using the critical path method (CPM) for evaluating allocation potential of temporary housing units. Journal of Housing and the Built Environment. https://doi.org/10.1007/s10901-025-10196-z

Purnomo, A. D. (2025). Legal Study of Telemedicine Implementation at XYZ Clinic in South Jakarta Based on the Perspective of Law 17 of 2023 concerning Health. Journal of Law and Humanity Studies, 2(1), 23-27. https://doi.org/10.59613/z5n8d627

Putra, G. R., Ariftiarno, R., Karlitasari, L., & Akhmad, D. M. (2025). Faculty information systems project management: A comparison of CPM and PERT methods. Komputasi: Jurnal Ilmiah Ilmu Komputer dan Matematika, 22(1), 12–20.

Raihan, M., & Sidabalok, A. S. (2025). Design and Build Project Scheduling Applications Using the Critical Path Method. Bigint Computing Journal, 3(2), 91-99. https://doi.org/10.55537/bigint.v3i2.1255

Rajala, R., & Westerlund, M. (2007). A business model perspective on knowledge-intensive services in the software industry. International Journal of Technoentrepreneurship, 1(1), 1-20. https://doi.org/10.1504/IJTE.2007.013267

Ren, Y., & Li, J. (2023). Research on software project schedule planning technology based on the integration of PERT and CPM. Procedia Computer Science, 228, 253–261. https://doi.org/10.1016/j.procs.2023.11.029

Rev, E. (2003). Work breakdown structure. U.S. Department of Energy.

Ridwan, A. (2025). Optimizing project time management using the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT). Jurnal Aplikasi Pelayaran dan Kepelabuhanan, 15(2), 354–361. https://doi.org/10.30649/japk.v15i2.160

Romadhani, O., Badi’ah, R., & Wicaksono, A. Y. (2025). Implementation of time management using the Critical Path Method (CPM) in the construction of school buildings. Jurnal Ekonomi Balance, 21(1). https://doi.org/10.26618/jeb.v21i1.17010

Sabila, D. A., Wirani, Y., & Sucahyo, Y. G. (2025). Assessment of Smart Waste Management System Maturity Levels: A Case Study at PT. XYZ. The Indonesian Journal of Computer Science, 14(1). https://doi.org/10.33022/ijcs.v14i1.4618

Seyyedi, A. Z. G., Gitizadeh, M., Fakhrooeian, M., & Nasero, M. J. (2025). Achieving the goals of energy arbitrage, peak-shaving, and PV self-consumption using PV-BTM BESS microgrids coupled with a distribution network. Journal of Energy Storage, 112, 115479. https://doi.org/10.1016/j.est.2025.115479

Sihombing, L. B., & Prabowo, B. N. (2026). Mitigating Engineering Phase Delays in EPC Projects: Monte Carlo Simulation Method with Project XYZ. ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering, 12(1), 05025003. https://doi.org/10.1061/AJRUA6.RUENG-1390

Soeharto, I. (1999). Manajemen proyek: Dari konseptual sampai operasional. Erlangga.

Soeharto, I. (2002). Studi kelayaan proyek industri. Erlangga.

Sugianto, A., Maslina, & Suprapto, L. M. (2021). Kajian pelaksanaan proyek pembangunan Puskesmas Margomulyo dengan metode CPM dan PERT. Jurnal Ilmiah Teknik Sipil TRANSUKMA, 4(1), 61–67.

Sugiarto, F. (2025). Integration of Qur'an and Hadith Values as Pedagogical Innovation to Improve the Quality of Islamic Education. QALAMUNA: Jurnal Pendidikan, Sosial, Dan Agama, 17(1), 171-184. https://doi.org/10.37680/qalamuna.v17i1.6817

Vazquez, A., Pozzana, I., Kalogridis, G., & Ellinas, C. (2023). Activity networks determine project performance. Scientific Reports, 13(1), 509. https://doi.org/10.1038/s41598-022-27180-0

Wendpanga Jacob, Y. O. U. G. B. A. R. E., Boureima, S. O. R. Y., & Moumouni, Z. O. N. G. O. (2024). COMPARATIVE ANALYSIS WITH THE PERT METHOD: TIMES CERTAIN VS UNCERTAIN. Advances & Applications in Discrete Mathematics, 41(2). https://doi.org/10.17654/0974165824008

Zareei, S. (2018). Project scheduling for constructing biogas plant using critical path method. Renewable and Sustainable Energy Reviews, 81, 756-759. https://doi.org/10.1016/j.rser.2017.08.025

Published
2026-07-08
How to Cite
Wagimin, W., & Fattah, A. (2026). Analysis of Improving the Efficiency and Effectiveness of Company Resource Utilization Using CPM and PERT Approaches: A Case Study. Journal La Multiapp, 7(3), 688-701. https://doi.org/10.37899/journallamultiapp.v7i3.3329