Scheduling Analysis Docking of the Leo Mariner Tug Boat Vessel at PT Using the Critical Path Method

  • Wagimin Program Studi Teknik Industri Universitas Balikpapan, Indonesia
  • Anwar Fattah Program Studi Teknik Elektro Universitas Balikpapan, Indonesia
Keywords: CPM, Scheduling, Ship Docking

Abstract

So far, ship docking work at the shipyard facility in XYZ has so far not implemented a project scheduling method to optimize performance. Determining the time and scheduling of ship docking work is done based on experience. As a result, there is time and cost inefficiency that impacts low performance, so that the docking and shipping industry is difficult to develop and contribute to the development of the maritime sector. This study aims to optimize the docking schedule of the Leo Mariner Tugboat. The method used is the Critical Path Method (CPM) to determine critical path. Research result shows that the Docking process under existing conditions has 24 activities and 21 paths that require a working time of 100.50 hours. Optimization using CPM produces a critical path with 10 activities and 9 paths that require a working time of 100.50 hours. work for 22.5 hours, or an efficiency of 4.8 % From the base This demonstrates that CPM successfully optimizes ship docking times This finding is beneficial for PT. XYZ in optimizing performance and supporting the development of Indonesia's maritime sector.

References

Ammar, M. A. (2013). LOB and CPM integrated method for scheduling repetitive projects. Journal of construction engineering and management, 139(1), 44-50. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000569

Anggoro, R., & Amrullah, R. A. (2023). Marine Transportation Human Resources (HR) Based On The World Maritime Axis. Jhss (Journal of Humanities and Social Studies), 7(1), 118-125. https://doi.org/10.33751/jhss.v7i1.7469

Armela, A. C., Amiruddin, W., & Hadi, E. S. (2022). Implementasi Project Evaluation and Review Technique (PERT) Pada Penjadwalan Reparasi Kapal KMP Royal Nusantara. Jurnal Teknik Perkapalan, 10(2), 68-76.

Bakken, T. H., Aase, A. G., Hagen, D., Sundt, H., Barton, D. N., & Lujala, P. (2014). Demonstrating a new framework for the comparison of environmental impacts from small-and large-scale hydropower and wind power projects. Journal of Environmental Management, 140, 93-101. https://doi.org/10.1016/j.jenvman.2014.01.050

Campos, I., Brito, M., & Luz, G. (2023). Scales of solar energy: Exploring citizen satisfaction, interest, and values in a comparison of regions in Portugal and Spain. Energy Research & Social Science, 97, 102952. https://doi.org/10.1016/j.erss.2023.102952

Farida, Y., & Anenda, L. P. (2022). Network planning analysis on road construction projects by CV. X using evaluation review technique (pert)-critical path method (CPM) and crashing method. International Journal of Integrated Engineering, 14(4), 377-390.

Firstdhitama, W., Suastika, I. K., & Ma'ruf, B. (2018). Perencanaan Penjadwalan Reparasi Kapal Ferry Dengan Menggunakan Metode Flash. Wave: Jurnal Ilmiah Teknologi Maritim, 12(1), 1-12.

Gonggong, A. (2020). Membangun Kembali Budaya Maritim Indonesia Dengan Strategi Maritim Indonesia. Jurnal Maritim Indonesia (Indonesian Maritime Journal), 8(2), 33-52.

Hanggarini, P., Madjid, M. A., Perwita, A. A. B., & Wiranto, S. (2022). Budaya maritim dan diplomasi maritim untuk kepentingan nasional. Indonesian Perspective, 7(2), 164-179. https://doi.org/10.14710/ip.v7i2.50777

Howick, S., Ackermann, F., Eden, C., & Williams, T. (2009). Understanding the causes and consequences of disruption and delay in complex projects: how system dynamics can help.

Hutapea, J. S., Mulyatno, I. P., & Manik, P. (2020). Studi Penjadwalan Ulang Pekerjaan Reparasi Pada Kapal MV. Awu Dengan Network Diagram Dan Critical Path Method (CPM). Jurnal Teknik Perkapalan, 8(4), 555-562.

Iqbal, N., Khan, A. N., Rizwan, A., Qayyum, F., Malik, S., Ahmad, R., & Kim, D. H. (2022). Enhanced time-constraint aware tasks scheduling mechanism based on predictive optimization for efficient load balancing in smart manufacturing. Journal of manufacturing systems, 64, 19-39. https://doi.org/10.1016/j.jmsy.2022.05.015

Istiqomah, M. R. M., Mulyatno, I. P., Sisworo, S. J., Hadi, E. S., Kiryanto, K., & Mursid, O. (2021). Penjadwalan Ulang Kapal Reparasi TB. Patra Tunda 3001 dengan Metode Jalur Kritis. Jurnal Teknologi Perikanan dan Kelautan, 12(2), 161-174. https://doi.org/10.24319/jtpk.12.161-174

Jebbor, I., Benmamoun, Z., & Hachimi, H. (2023). Optimizing manufacturing cycles to improve production: Application in the traditional shipyard industry. Processes, 11(11), 3136. https://doi.org/10.3390/pr11113136

Lock, D. (1987). Manajemen Proyek, edisi ketiga. Jakarta (ID): Erlangga.

Manurung, H. (2014). Joko Widodo National Leaderships on Indonesia's World Maritime Policy. Available at SSRN 2510986. https://dx.doi.org/10.2139/ssrn.2510986

Muhammad, A. B. M. S. A. (2020). Analisa Perhitungan Pekerjaan Reparasi Kapal Dengan Metode Critical Path Method (CPM): cpm. SPECTA Journal of Technology, 4(1), 84-91. https://doi.org/10.35718/specta.v4i1.172

Napitupulu, P., & Lubis, Y. (2022). Perencanaan Durasi Waktu Pembangunan Rumah Type 70. Jurnal Teknik Sipil (JTSIP), 1(1).

Nudin, M. I. (2023). Optimasi Penjadwalan Ulang Reparasi Tug Boat 296 Gt Dengan Menggunakan Metode Cpm (Critical Path Method) Dan Metode PDM (Precedence Diagram Method) (Doctoral dissertation, Politeknik perkapalan Negeri Surabaya).

Oktafiana, L. O., & Baroroh, I. (2022). Comparative Analysis of CPM, PDM and PERT Methods in Ship Repair Scheduling Planning KN. RB 309 Ternate 01. Berkala Sainstek, 10(3), 162-174.

Panayides, P. M., & Cullinane, K. (2002). Competitive advantage in liner shipping: a review and research agenda. International journal of maritime economics, 4(3), 189-209. https://doi.org/10.1057/palgrave.ijme.9100045

Pangemanan, A. E. (2019). Kebijakan maritim dalam mewujudkan negara kesatuan republik indonesia sebagai poros maritim dunia. Lex Et Societatis, 7(12). https://doi.org/10.35796/les.v7i12.27573

Peters, H. J. (2001). Developments in global seatrade and container shipping markets: their effects on the port industry and private sector involvement. International Journal of Maritime Economics, 3(1), 3-26. https://doi.org/10.1057/palgrave.ijme.9100003

Rodney Turner, J., Ledwith, A., & Kelly, J. (2009). Project management in small to medium‐sized enterprises: A comparison between firms by size and industry. International Journal of Managing Projects in Business, 2(2), 282-296. https://doi.org/10.1108/17538370910949301

Santosa, A. W. B., Mursid, O., Kalingga, M. A., Ahmad, S. T. P., & Trimulyono, A. (2023). Productivity Analysis Using the Critical Chain Project Method Management (CCPM) on Repair Projects Geomarin-III ship 649 DWT. International Journal of Marine Engineering Innovation and Research, 8(1), 80-87.

Shahri, A. A. (2022). Analysis of Activity Planning In the 2765 Dwt Tanker Repair Process Using the Critical Path Method (Cpm) shipyard; critical path method (cpm); project scheduling. Indonesian Vocational Research Journal, 2(1), 163-172.

Shobrys, D. E., & White, D. C. (2002). Planning, scheduling and control systems: why cannot they work together. Computers & chemical engineering, 26(2), 149-160. https://doi.org/10.1016/S0098-1354(01)00737-2

Simion, M., Vasile, G., Dinu, C., & Scutariu, R. (2019). CPM and PERT techniques for small-scale R&D projects.

Sitanggang, S. N. (2023). Jokowi Administration's Maritime Axis Development Policy. Inspirasi & Strategi (INSPIRAT): Jurnal Kebijakan Publik & Bisnis, 13(2), 71-83. https://doi.org/10.35335/inspirat.v13i2.20

Soni, A. K. A. S. H., Ramesh Kumar, C., & Shrivastava, A. M. I. T. (2022). Construction projects risk assessment based on PERT, CPM and project management with Fuzzy Logic technique. Advances and Applications in Mathematical Sciences, 21(9), 5385-5395.

Suyuti, A. M., & Basuki, M. (2022, March). Analisis Perbandingan Penjadwalan Proyek Dengan Critical Path Methode (CPM) dan Critical Chain Project Management (CCPM) Pada Reparasi Kapal BG. KFT 8005. In Prosiding SENASTITAN: Seminar Nasional Teknologi Industri Berkelanjutan (Vol. 2, pp. 152-165).

Turner, R., & Zolin, R. (2012). Forecasting success on large projects: developing reliable scales to predict multiple perspectives by multiple stakeholders over multiple time frames. Project management journal, 43(5), 87-99. https://doi.org/10.1002/pmj.21289

Wu, W. M., & Lin, J. R. (2015). Productivity growth, scale economies, ship size economies and technical progress for the container shipping industry in Taiwan. Transportation Research Part E: Logistics and Transportation Review, 73, 1-16. https://doi.org/10.1016/j.tre.2014.10.011

Xiao, G., Wang, Y., Wu, R., Li, J., & Cai, Z. (2024). Sustainable maritime transport: A review of intelligent shipping technology and green port construction applications. Journal of Marine Science and Engineering, 12(10), 1728. https://doi.org/10.3390/jmse12101728

Yani, Y. M., & Montratama, I. (2015). Indonesia sebagai poros maritim dunia: suatu tinjauan geopolitik. Jurnal Pertahanan dan Bela Negara, 5(2), 25-52. https://doi.org/10.33172/jpbh.v5i2.356

Published
2026-02-04
How to Cite
Wagimin, W., & Fattah, A. (2026). Scheduling Analysis Docking of the Leo Mariner Tug Boat Vessel at PT Using the Critical Path Method. Journal La Multiapp, 7(1), 199-207. https://doi.org/10.37899/journallamultiapp.v7i1.2841