Waste Analysis in Connection Clamp Production Process with Lean Manufacturing and Failure Mode Effect Analysis

  • Faishal Hidayatulloh Department of Industrial Engineering, Faculty of Engineering, UPN “Veteran” East Java Rungkut Menanggal, Gn. Anyar District, Surabaya, East Java 60293, Indonesia
  • Rr. Rochmoeljati Department of Industrial Engineering, Faculty of Engineering, UPN “Veteran” East Java Rungkut Menanggal, Gn. Anyar District, Surabaya, East Java 60293, Indonesia
Keywords: Lean Manufacturing, Waste Assesment Model, Failure Mode Effect Analysis, Manufacturing, Connection Clamp

Abstract

UD H and M Electric is a manufacturing company engaged in the production of medium voltage overhead line (SUTM) components, one of its products is the Connection Clamp. The purpose of this study is to determine the level of waste that occurs and provide suggestions for improvements to reduce waste. The research data used is questionnaire data with respondents who meet the qualifications and know the entire flow of the Connection Clamp production process, as well as waste data that occurs during the production process. To determine the level of waste that occurs and provide suggestions for improvements, the Waste Assessment Model, Process Activity Mapping, Fishone Diagram, and Failure Mode and Effect Analysis methods are used. In the Waste Assessment Model method, the top three critical levels of waste were obtained, namely waste defect of 19.55%, waste motion of 16.88%, waste transportation of 16.10%. In the Failure Mode and Effect Analysis, the Risk Priority Number (RPN) value was obtained from the top three wastes with each sub-waste, namely waste motion sub-waste lifting products manually with a score of 280, waste motion sub-waste rearranging before the process with a score of 240, waste transport, namely the distance of the work station is less than optimal with a score of 200, waste reject sub-waste cracked plates with a score of 168, waste Defect, namely imperfect layers with a score of 168.

References

Afriandi, F., & Saifuddin, J. A. (2023). Penerapan Lean Manufacturing Menggunakan Metode Waste Assessment Model (WAM) Untuk Mengurangi Waste Pada Lini Produksi Steel Structure. Jurnal Teknik Mesin, Industri, Elektro dan Informatika, 2(4), 62-75. https://doi.org/10.55606/jtmei.v2i4.2930

Alriwanda, Saputra, E., & Ahsyar, T. K. (2024). Analisa Manajemen Resiko Keamanan Sistem Informasi Baznas Kampar dengan Metode Failure Mode And Effect Analysis ( FMEA ). Jurnal Penerapan Sistem Informasi (Komputer & Manajemen), 5(3), 1225–1232.

Baharun, H., & Hasanah, R. (2023). Quality Improvement in Increasing Public Trust Using the Failure Mode and Effect Analysis (FMEA) Method. Tarbawi: Jurnal Keilmuan Manajemen Pendidikan, 9(01), 59-68. https://doi.org/10.32678/tarbawi.v9i01.7982

Cardiel-Ortega, J. J., & Baeza-Serrato, R. (2023). Failure mode and effect analysis with a Fuzzy Logic approach. Systems, 11(7), 348.

Ciliberto, C., Szopik‐Depczyńska, K., Tarczyńska‐Łuniewska, M., Ruggieri, A., & Ioppolo, G. (2021). Enabling the Circular Economy transition: A sustainable lean manufacturing recipe for Industry 4.0. Business Strategy and the Environment, 30(7), 3255-3272. https://doi.org/10.1002/bse.2801

Dancer, W. T., Chopra, H., & Duong, A. (2024). The Value of Non-Value Activities. Journal of Accounting & Finance (2158-3625), 24(5). https://doi.org/10.33423/jaf.v24i5.7364

Dara, H. M., Adamu, M., Ingle, P. V., Raut, A., & Ibrahim, Y. E. (2025). An MCDM Approach to Lean Tool Implementation for Minimizing Non-Value-Added Activities in the Precast Industry. Infrastructures, 10(3), 55. https://doi.org/10.3390/infrastructures10030055

Firdaus, R. Z., Wahyudin, W., & Zani, R. (2023). Penerapan Konsep Lean Manufacturing untuk Meminimasi Waste pada PT Anugerah Damai Mandiri ( ADM ) Applying Lean Manufacturing Concepts to Minimize Waste in PT Anugerah Damai Mandiri ( ADM ). Journal of Integrated System (JIS), 6(1), 21–31. https://doi.org/10.28932/jis.v6i1.5632

Gao, G., Feng, Y., Zhang, Z., Wang, S., & Yang, Z. (2023). Integrating SLP with simulation to design and evaluate facility layout for industrial head lettuce production. Annals of operations research, 321(1), 209-240. https://doi.org/10.1007/s10479-022-04893-z

Gomaa, A. H. (2025). Enhancing Failure Mode and Effects Analysis with Industry 4.0 (FMEA 4.0): A Comprehensive Review and Strategic Framework. International Journal of Darshan Institute of Engineering Research and Emerging Technologies, 14(2), 1-12. https://doi.org/10.32692/IJDI-ERET/14.2.2025.2501

Hartanti, L. P. S., Mulyono, J., & Mayang, V. (2022). Penerapan Fmea Dan Fuzzy Fmea Dalam Penilaian Risiko Lean Waste Di Industri Manufaktur. JST (Jurnal Sains Dan Teknologi), 11(2), 293–304. https://doi.org/10.23887/jstundiksha.v11i2.50552

Hemalatha, C., Sankaranarayanasamy, K., & Durairaaj, N. (2021). Lean and agile manufacturing for work-in-process (WIP) control. Materials Today: Proceedings, 46, 10334-10338. https://doi.org/10.1016/j.matpr.2020.12.473

Hidayati, A. N. N., & Nurhidayat, A. E. (2021). Analisis Penyebab Kecacatan Produksi Permen Yupi Dengan FTA, Fuzzy-FMEA dan WAM. J. Optimasi Tek. Ind, 3(02), 70-75.

Hidayatullah, M. A., & Widjajati, E. P. (2024). Lean Manufacturing Analysis Using Waste Assessment Model (WAM) and Root Cause Analysis (RCA) Methods. Rekayasa, 17(2), 240-249. https://doi.org/10.21107/rekayasa.v17i2.25657

Irawan, Y. B., & Fitriani, K. (2024). Waste Assessment Model (WAM): How Does the Company Assess the Waste?. Jurnal Sains & Teknologi Lingkungan, 16(2), 54-68. https://doi.org/10.20885/jstl.vol16.iss2.art4

Jatmiko, L. V. P., & Safirin, M. T. (2025). Waste Reduction in the Sickle Production Process Using the VALSAT Method and Value Stream Mapping. Golden Ratio of Data in Summary, 5(2), 08-15. https://doi.org/10.52970/grdis.v5i2.936

Khunaifi, A., Rangga Primadasa, & Sugoro Bhakti Sutono. (2022). Implementasi Lean Manufacturing untuk Meminimasi Pemborosan (Waste) Menggunakan Metode Value Stream Mapping di PT. Pura Barutama. Jurnal Rekayasa Industri (JRI), 4(2), 87–93. https://doi.org/10.37631/jri.v4i2.560

Kurnia, I. (2023). Basic Lean Manufacturing, 2023. In Bahan Ajar Basic Lean Manufacturing, 2023. https://repository.unkris.ac.id/id/eprint/536/1/Bahan Ajar Lean Manufacturing.pdf

Macedo, H., Tomaz, L., Guimarães, L., Cerqueira-Pinto, L., Sá, J. C., & Dinis-Carvalho, J. (2025). Development of a Classification Model for Value-Added and Non-Value-Added Operations in Retail Logistics: Insights from a Supermarket Case Study. Sustainability, 17(7), 3177. https://doi.org/10.3390/su17073177

Mansur, M., Ahmarofi, A. A., & Gui, A. (2021). Designing the re-layout of the production floor using integrated systematic layout planning (SLP) and simulation methods. International Journal of Industrial Management, 10, 151-159. https://doi.org/10.15282/ijim.10.1.2021.6058

Maulana, M., Suhendar, E., & Prasasty, A. T. (2023). Penerapan Lean Management Untuk Meminimasi Waste Pada Lini Produksi CV. Mandiri Jaya Dengan Metode WAM Dan VALSAT. Jurnal Optimasi Teknik Industri (JOTI), 5(1), 1. https://doi.org/10.30998/joti.v5i1.13747

Naziihah, A., Arifin, J., & Nugraha, B. (2022). Identifikasi Waste Menggunakan Waste Assessment Model (WAM) di Warehouse Raw Material PT. XYZ. Jurnal Media Teknik Dan Sistem Industri, 6(1), 30–40. https://doi.org/10.35194/jmtsi.v6i1.1599

Nelfiyanti, N., Saputra, D., & Puteri, R. A. M. (2023). Penerapan Value Stream Mapping Tools dalam Meminimasi Pemborasan Proses Packing Part Disc di line Servis. JISI: Jurnal Integrasi Sistem Industri, 10(1), 9–18. https://doi.org/10.24853/jisi.10.1.9-18

Pical, A. J., Irawati, D. Y., & Andrian, D. (2025). Lean Manufacturing Analysis: Using WAM and VALSAT to Reduce Waste in the Plastic Sack Finishing Process at PT Surya Plastindo. Engineering Headway, 18, 153-162. https://doi.org/10.4028/p-nKM8rh

Pratiwi, Y., Djanggu, N. H., & Anggela, P. (2020). Penerapan Lean Manufacturing Untuk Meminimasi Pemborosan (Waste) Dengan Menggunakan Metode Value Stream Mapping (Vsm) Pada Pt. X. Jurnal Teknik Industri Universitas Tanjungpura, 4(2), 8–15. https://jurnal.untan.ac.id/index.php/jtinUNTAN/article/view/42196

Putro, A. M. S., & Nursyamsiah, S. (2024). Analisis Implementasi Lean Manufacturing Dengan Metode 5s Pada Startup Manufaktur Di Indonesia. 8(3), 1800–1817.

Rahardjo, B., Wang, F. K., Yeh, R. H., & Chen, Y. P. (2023). Lean manufacturing in industry 4.0: a smart and sustainable manufacturing system. Machines, 11(1), 72.

Rahman, A. D., Marlyana, N., & Mas’idah, E. (2024). Penerapan Lean Manufacturing Untuk Meningkatkan Efisiensi Pada Proses Produksi Garmen Pt.Xyz. Jurnal Ilmiah Sultan Agung, 591–609.

Rodriguez, A. R. S. C., & Oliveira, P. V. D. (2022). An extension of systematic layout planning by using fuzzy AHP and fuzzy VIKOR methods: a case study. European Journal of Industrial Engineering, 16(1), 1-30. https://doi.org/10.1504/EJIE.2022.119368

Salsabila, I. R., & Rochmoeljati, R. (2021). Analisis Penerapan Konsep Lean Manufacturing Pada Proses Produksi Stainless Steel Coil Untuk Mereduksi Pemborosan (Waste) Di Pt. Xyz. Juminten : Jurnal Manajemen Industri Dan Teknologi, 2(2), 120–131. https://doi.org/10.33005/juminten.v2i2.235

Samimi, A. (2025). Application of failure mode and effects analysis (FMEA) for risk management in hospital laboratories. Medicinal, Psychological, and Health Research Journal (mphrj), 1(5), 160-168. https://doi.org/10.22034/mphrj.2025.532521.1021

Sampeallo, Y. G., & Hasiara, L. O. (2024). Manajemen Produksi. PT Media Penerbit Indonesia.

Suparno, A., Kholil, M., & Hasan, S. B. H. (2021). Implementation of lean manufacturing and waste minimization to overcome delay in metering regulating system fabrication process using value stream mapping and VALSAT method approach (Case Study: Company YS). International Journal of Advanced Technology in Mechanical, Mechatronics and Materials, 2(1), 22-34. https://doi.org/10.37869/ijatec.v2i1.41

Suradi. (2022). Sistem Produksi. In Marhamah (Ed.), Cetakan Pertama, Yogyakarta; Graha Ilmu, (Vol. 1, Issue January 2022). CV. Tohar Media.

Syaproni, M. F., Suhendar, E., & Hartini, S. (2024). Analisis Penerapan Lean Warehouse Untuk Meminimasi Waste Pada Gudang PT. Artaprima Cipta Caturindo Dengan Metode Value Stream Mapping (VSM) dan Waste Assesment Model (WAM). Jurnal Pemasaran Bisnis, 6(4). https://doi.org/10.55826/jtmit.v4i4.938

Taher, M. A., & Bashar, M. A. (2024). The impact of lean manufacturing concepts on industrial processes’ efficiency and waste reduction. International Journal of Progressive Research in Engineering Management and Science, 4(6), 338-349.

Published
2026-01-19
How to Cite
Hidayatulloh, F., & Rochmoeljati, R. (2026). Waste Analysis in Connection Clamp Production Process with Lean Manufacturing and Failure Mode Effect Analysis. Journal La Multiapp, 7(1), 12- 29. https://doi.org/10.37899/journallamultiapp.v7i1.2820