Cost and Time Performance Analysis Using the Earned Value Concept in the Construction of the Integrated Lecture Building at the State Polytechnic of Shipbuilding Surabaya

  • Victor Fajar Bahari Civil Engineering Study Program, Muhammadiyah University of Sidoarjo, Indonesia
  • Muhammad Alvan Rizki Civil Engineering Study Program, Muhammadiyah University of Sidoarjo, Indonesia
Keywords: Time and Cost Control, GKT, Actual Cost, Earned Value

Abstract

Time and cost control is an important aspect in the success of construction projects, especially in large-scale projects such as the construction of the Integrated Lecture Building (GKT) of Surabaya State Polytechnic of Shipping. This research aims to analyze the time and cost performance of the project using the earned value concept. With this method, measurement and evaluation of project performance can be done quantitatively based on earned value data. The results of the analysis show that from the evaluation results in the 35th week, the value of ACWP is Rp. 47,741,219,980.93, the BCWP value is Rp. 47,874,478,839.55, and the BCWS value is Rp. 47,721,477,927.80. Based on the ACWP, BCWP, and BCWS values, the Cost Variance (CV) value is Rp. 133,258,858.63 and the Schedule Variance (SV) is Rp. 153,00,911.76. This figure indicates that the costs incurred are more efficient and the implementation time is faster than planned. The values of CPI and SPI equal to 1.00 indicate good cost performance within budget as well as good schedule performance with the schedule on time against the plan. The estimated cost of ETC is Rp. 1,476,532,576.73 and EAC is Rp. 49,217,752,557.66. The estimated time of ETS is Rp. 1.99 weeks and EAS is 36.99 weeks. With the application of this method, deviations from schedule and budget can be identified early so that decision making can be done appropriately to return the project to the predetermined schedule.

References

Akpe, A. T., Nuan, S. I., Solanke, B., & Iriogbe, H. O. (2024). Development and implementation of cost control strategies in oil and gas engineering projects. Global Journal of Advanced Research and Reviews, 2(01), 001-022. https://doi.org/10.58175/gjarr.2024.2.1.0028

Al Wahid, S. A., Mohammad, N., Islam, R., Faisal, M. H., & Rana, M. S. (2024). Evaluation of information technology implementation for business goal improvement under process functionality in economic development. Journal of Data Analysis and Information Processing, 12(2), 304-317. https://doi.org/10.4236/jdaip.2024.122017

Alwan, A., Jallah, W., Baltussen, R., Carballo, M., Gonyon, E., Gudumac, I., ... & Skordis, J. (2024). Designing an evidence-informed package of essential health services for Universal Health Coverage: lessons learnt and challenges to implementation in Liberia. BMJ Global Health, 9(6).

Arifin, M. F. A., Sarifatuzzuhriyah, M., & Liu, S. S. (2023). Cost and time control analysis with earned value method in the MRT-Hub building construction. Jurnal Teknik Sipil dan Perencanaan, 25(1), 90–99. https://doi.org/10.15294/jtsp.v25i1.43043

Ayni, W. N., Suranata, P. G., & Armaeni, N. K. (2019). Analisis kinerja pelaksanaan proyek dengan menggunakan metode earned value concept (Studi kasus pembangunan Gedung Kantor Perwakilan Bank Indonesia Provinsi). Jurnal Paduraksa, 8(1), 94–103.

Borysenko, A. S., Masrar, M., & El Akhal, R. (2025). CRISIS OF ACCESS TO MODERN EDUCATIONAL COMPLEXES: EXPOSING THE GAPS. Municipal economy of cities. Series:«Information Technology and Engineering», 1(189), 139-149. https://doi.org/10.33042/2522-1809-2025-1-189-139-149

Choiriyah, S., Listyaningsih, D., Nuciferani, F., Ferdaus, F., Perdana, G. S., & Sekartadji, R. (2024). Performance Evaluation of Projects using Earned Value Concept. Jurnal Teknologi dan Manajemen, 5(1), 21-30. https://doi.org/10.31284/j.jtm.2024.v5i1.4620

Dugbartey, A. N., & Kehinde, O. (2025). Optimizing project delivery through agile methodologies: Balancing speed, collaboration and stakeholder engagement. World J. Adv. Res. Rev, 25, 1237-1257. https://doi.org/10.30574/wjarr.2025.25.1.0193

Glavan, B., Iordache, A. M. M., Anghel, F., Grigorescu, I. G., Ionescu, A., & Nechita, R. (2024). Government-Funded Businesses: An Empirical Study of Romanian Start-Ups. Engineering Economics, 35(1), 45-64. https://doi.org/10.5755/j01.ee.35.1.32034

Kamila, J. S., & Marzuq, M. F. (2024). Asana and Trello: a comparative assessment of project management capabilities. JOIV: International Journal on Informatics Visualization, 8(1), 207-212. https://dx.doi.org/10.62527/joiv.8.1.2595

Latilo, A., Uzougbo, N. S., Ugwu, M. C., Oduro, P., & Aziza, O. R. (2024). Developing legal frameworks for successful engineering, procurement, and construction projects. Int J Appl Res Soc Sci, 6(8), 1868-1883.

Li, W. (2023). Application of earned value management in project management. Advances in Economics, Management and Political Sciences, 20(1), 101–109. https://doi.org/10.54254/2754-1169/20/20230178

Pal, A., Lin, J. J., Hsieh, S. H., & Golparvar-Fard, M. (2024). Activity-level construction progress monitoring through semantic segmentation of 3D-informed orthographic images. Automation in Construction, 157, 105157. https://doi.org/10.1016/j.autcon.2023.105157

Pandjaitan, P. D. B., & Zuhdy, A. Y. (2023). Perhitungan waktu dan biaya pelaksanaan pembangunan Gedung Trans Icon Surabaya Tower A lantai 20–29 dengan metode konstruksi half slab precast. Jurnal Teknik ITS, 12(1). https://doi.org/10.12962/j23373539.v12i1.109466

Popoola, O. A., Adama, H. E., Okeke, C. D., & Akinoso, A. E. (2024). Cross-industry frameworks for business process reengineering: Conceptual models and practical executions. World Journal of Advanced Research and Reviews, 22(01), 1198-1208. https://doi.org/10.30574/wjarr.2024.22.1.1201

Pramesthi, K. M. D., & Chaullah, A. (2021). Tutorial pengendalian waktu dan biaya proyek menggunakan metode earned value (p. 30). Departemen Teknik Sipil.

Pribadi, R. A., & Abduh, M. (2022). Analisis Cost Performance Index (CPI) dan Schedule Performance Index (SPI) menggunakan metode earned value (Studi kasus pada proyek pembangunan Gedung Pasar Bucor Kulon Kabupaten Probolinggo). Jurnal Media Teknik Sipil, 20(1), 14–23. https://doi.org/10.22219/jmts.v20i1.14620

Proboretno, W., Witjaksana, B., & Tjendani, H. T. (2024). Time performance analysis on afv earthwork in kedungpeluk sidoarjo using the earned value method. Journal Of Humanities, Social Sciences And Business, 3(2), 465-475.

Ruso, J., Filipović, J., & Pejović, G. (2017). The role of higher education in national quality infrastructure policy-making. Management: Journal of Sustainable Business and Management Solutions in Emerging Economies, 22(1), 15-24. https://doi.org/10.7595/management.fon.2017.0003

Sandanayake, M., Bouras, Y., & Vrcelj, Z. (2022). Environmental sustainability in infrastructure construction—a review study on Australian higher education program offerings. Infrastructures, 7(9), 109. https://doi.org/10.3390/infrastructures7090109

Soetjipto, J. W., Adinanda, D. A., & Arifin, S. (2024). Pengendalian penyelesaian proyek berbasis kinerja menggunakan hybrid earned value - crash program. Jurnal Aplikasi Teknik Sipil, 22(2), 127. https://doi.org/10.12962/j2579-891x.v22i2.15996

Sri Mahapatni, I. A. P., Putra, C., & Murwanta, K. E. (2022). Analisis kinerja waktu dan biaya pelaksanaan proyek dengan metode earned value pada proyek pembangunan Jembatan Pangkung Dalem Ruas Jalan Gitgit–Wanagiri. Jurnal Ilmiah Kurva Teknik, 11(2), 17–25. https://doi.org/10.36733/jikt.v11i2.5424

Stevens, C. (2024). Comparing Design Studios: Analyzing Relationships Between Institutional Ambitions and Building Design (Master's thesis, State University of New York at Buffalo).

Sugiyanto, A., & Gondokusumo, O. (2020). Perbandingan metode earned value, earned schedule, dan Kalman filter earned value untuk prediksi durasi proyek. JMTS: Jurnal Mitra Teknik Sipil, 3(1), 155. https://doi.org/10.24912/jmts.v3i1.7069

Xianhe, M. (2024). Construction Management Characteristics and Quality Control Strategies for Higher Education Infrastructure Projects. International Journal of New Developments in Engineering and Society, 8(2). https://doi.org/DOI:10.25236/IJNDES.2024.080202

Yilmaz, S., Kumar, D., Hada, S., Demirkesen, S., Zhang, C., & Li, H. (2025). A PMBOK-based construction cost management framework for BIM integration in construction projects. International Journal of Construction Management, 25(8), 861-875. https://doi.org/10.1080/15623599.2024.2371626

Yuliana, C., Hapsari, R., & Agustina, R. (2019). Analisis kinerja biaya dan waktu terpadu dengan konsep nilai hasil pada proyek konstruksi di lahan rawa. Jurnal Kajian Teknik Sipil, 4(2), 176–183. https://doi.org/10.52447/jkts.v4i2.1656

Published
2025-07-17
How to Cite
Bahari, V. F., & Rizki, M. A. (2025). Cost and Time Performance Analysis Using the Earned Value Concept in the Construction of the Integrated Lecture Building at the State Polytechnic of Shipbuilding Surabaya . Journal La Multiapp, 6(3), 701-713. https://doi.org/10.37899/journallamultiapp.v6i3.2154