Analysis Planning Relay Layout with Computerized Relative Allocation of Facilities Technique Approach

  • Rigel Saesaria Marcelani Universitas Pembangunan Nasional "Veteran" Jawa Timur
  • Joumil Aidil SZS Universitas Pembangunan Nasional “Veteran” Jawa Timur
  • Yekti Condro Winursito Universitas Pembangunan Nasional “Veteran” Jawa Timur
Keywords: Layout Facilities, OMH, Moments Distance, Displacement, CRAFT

Abstract

PT XYZ is one of the manufacturing industries engaged in the production of palm oil processing. The products produced are cooking oil and margarine. So far, the implementation of activities has been hampered by the current layout conditions having a less efficient material handling path length, in addition, the distance between facilities is too far ± 150m which results in repeated transportation, this results in PT XYZ's material transfer activities being less effective. Therefore, this study aims to redesign the layout of production facilities in order to minimize material handling costs and raw material movement distances to be more effective. From these problems, the method used is the CRAFT (Computerized Relative Allocation of Facilities Techniques) method, this method can be done with the help of FTC (From to Chart), ARC (Activity Relation Chart) and ARD (Activity Relationship Diagram) calculations. The results of this study showed that the CRAFT algorithm succeeded in saving total material handling costs of Rp. 469,352.04 per day and reducing the total distance of movement by 67.15 meters. The reduction in material handling costs achieved was Rp 2,114,734.77 or around 81.84%, while the reduction in material handling distance reached 306.85 meters or around 82.05%.

References

Abdul Rahman, N. S. F., Karim, N. H., Md Hanafiah, R., Abdul Hamid, S., & Mohammed, A. (2023). Decision analysis of warehouse productivity performance indicators to enhance logistics operational efficiency. International Journal of Productivity and Performance Management, 72(4), 962-985. https://doi.org/10.1108/IJPPM-06-2021-0373

Hartini, S., Atikah, A., & Tiara, T. (2023). Desain Tata Letak Gudang untuk Meminimalkan Ongkos Material Handling pada PT. Rotaryana Prima. eCo-Fin, 5(2), 91-103. https://doi.org/10.32877/ef.v5i2.763

Hutabarat, J. (2022). Pengantar Teknik Industri. Media Nusa Creative (MNC Publishing).

Kulsum, K., & Tola, D. (2019). Relayout workshop produksi dengan menggunakan metode Craft. Journal Industrial Servicess, 5(1), 81-87. http://dx.doi.org/10.36055/jiss.v5i1.6507

Maimon, O., Khmelnitsky, E., & Kogan, K. (1998). Optimal flow control in manufacturing systems: Production planning and scheduling (Vol. 18). Springer Science & Business Media. https://doi.org/10.1007/978-1-4757-2834-7

Mourato, J., Pinto Ferreira, L., Sá, J. C., Silva, F. J., Dieguez, T., & Tjahjono, B. (2021). Improving internal logistics of a bus manufacturing using the lean techniques. International Journal of Productivity and Performance Management, 70(7), 1930-1951. https://doi.org/10.1108/IJPPM-06-2020-0327

Noer, M. F., Perdana, S., & Rahman, A. (2024). Perancangan Ulang Tata Letak Fasilitas Produksi Stainless Steel Menggunakan Metode SLP dan CRAFT. STRING (Satuan Tulisan Riset dan Inovasi Teknologi), 9(1), 124-132. http://dx.doi.org/10.30998/string.v9i1.24477

Nurahman, G. G. (2021). Peningkatan Efisiensi Biaya Transportasi Dengan Pemindahan Material Fast Moving Dari Gudang Mundu Ke Field Tambun Di PT. Pertamina EP Regional 2 Zona 7 Field Tambun (Doctoral dissertation, Institut Teknologi Sains Bandung).

Pitale, A. M., Parida, M., & Sadhukhan, S. (2022). GIS-MCDM–based approach to determine the potential facility locations for park-and-ride facilities along transit corridors. Journal of Urban Planning and Development, 148(1), 05021065. https://doi.org/10.1061/(ASCE)UP.1943-5444.000079

Rachmawaty, D., Saputra, M. A., & Karima, H. Q. (2022). Perancangan Tata Letak Fasilitas Pada UMKM Sepatu “Prohana” menggunakan Systematic Layout Planning. Matrik: Jurnal Manajemen Dan Teknik Industri Produksi, 23(1), 85-98. http://dx.doi.org/10.30587/matrik.v23i1.4072

Saputra, I. F. (2019). Rancang Ulang Tata Letak Fasilitas Pabrik Menggunakan Pairwise Exchange Dan Simulasi (Studi Kasus: Cv. Gemilang Vulkanisir) (Doctoral dissertation, Universitas Islam Negeri Sultan Syarif Kasim Riau).

Siagian, M. F., Zakaria, M., & Bakhtiar, B. (2022). Perancangan Ulang Tata Letak Pabrik Dengan Metode Sistematic Layout Planning Dan Computerized Relative Allocation Of Facilities Techniques Untuk Meningkatkan Efisiensi Produksi Di Pt. Abad Jaya Abadi SENTOSA. Industrial Engineering Journal, 11(1). https://doi.org/10.53912/iej.v11i1.720

Kamaruddin, S., Khoo, S. Y., Khan, Z. A., & Siddiquee, A. N. (2011). The effect of layout design on productivity: an empirical study. International Journal of Productivity and Quality Management, 7(4), 484-500. https://doi.org/10.1504/IJPQM.2011.040545

Prijanisa, A. A., Salsabila, F., Ramadhan, S. B., & Lastiati, A. (2024). ANALISIS ACTIVITY-BASED WORKPLACES (ABW) UNTUK MENINGKATKAN PRODUKTIVITAS KARYAWAN (PT YUMMY FOOD UTAMA). E-Prosiding Akuntansi, 5(2). https://doi.org/10.31326/.v5i2.2003

Fajarika, D., Gusvita, R., & Sofriani, N. (2019). Perancangan Tata Letak Laboratorium Pakan dengan Metode Computerized Relationship Layout Planning di Industri Penggemukan Sapi. Journal of Science and Applicative Technology, 3(2), 68-77. https://doi.org/10.35472/jsat.v3i2.123

Sihombing, E. A. (2023). Perancangan Ulang Tata Letak Fasilitas Produksi Tahu Untuk Meminimalkan Biaya Material Handling Menggunakan Algoritma Blocplan (Studi Kasus: Industri Kecil Tahu “Pak Ponimin”) (Doctoral dissertation, Universitas Medan Area).

Cano, J. A., Gómez, R. A., & Cortés, P. (2021, November). Ict validation in logistics processes: Improvement of distribution processes in a goods sector company. In Informatics (Vol. 8, No. 4, p. 75). MDPI. https://doi.org/10.3390/informatics8040075

Wali, L., & Lukmandono, L. (2023, March). Desain Ulang Tata Letak Fasilitas Produksi Dengan Metode CRAFT Untuk Meningkatkan Kapasitas Produksi Agregat. In Prosiding SENASTITAN: Seminar Nasional Teknologi Industri Berkelanjutan (Vol. 3).

Published
2024-02-02
How to Cite
Marcelani, R. S., Joumil Aidil SZS, & Yekti Condro Winursito. (2024). Analysis Planning Relay Layout with Computerized Relative Allocation of Facilities Technique Approach. Journal La Multiapp, 5(1), 44-56. https://doi.org/10.37899/journallamultiapp.v5i1.1588